| The following is the anticipated schedule for the NASA Johnson Space Center - Environmental Compliance and Operations (ECO) Contract. This schedule is subject to change. Please continue to monitor the following website, procurement.jsc.nasa.gov/eco/ as the schedule and solicitation will be posted there. |
| Milestone | Plan | Actual |
| Issue Draft Request for Proposal | 05/21/10 | 05/21/10 |
| Pre-Proposal Conference | 06/15-17/10 | 06/15-17/10 |
| Comments on Draft RFP Due | 06/22/10 | 06/22/10 |
| Issue Final Request for Proposal (RFP) | 08/02/10 | 07/27/10 |
| Past Performance Volume Due | 08/30/10 | 08/27/10 |
| Proposals Due | 09/14/10 | 09/16/10 |
| Contract Award | 02/15/11 | |
| Phase-In Start | 03/01/11 | |
| Contract Start | 05/01/11 |
|