Rotary Actuators
(Schedule Dates are Subject to Change)
The following is the anticipated schedule for the NASA Johnson Space Center - Environmental Compliance and Operations (ECO) Contract. This schedule is subject to change.  Please continue to monitor the following website, procurement.jsc.nasa.gov/eco/ as the schedule and solicitation will be posted there.
Milestone Plan Actual
Issue Draft Request for Proposal 05/21/10 05/21/10
Pre-Proposal Conference 06/15-17/10 06/15-17/10
Comments on Draft RFP Due                      06/22/10 06/22/10
Issue Final Request for Proposal (RFP) 08/02/10 07/27/10
Past Performance Volume Due                 08/30/10 08/27/10
Proposals Due 09/14/10 09/16/10
Contract Award 02/15/11  
Phase-In Start 03/01/11  
Contract Start 05/01/11  